Resource Assignment View
Description
The Resource Assignment View displays the scheduled task-resource assignments.
Data
The following columns are displayed as default:
Column | Description |
Name | The name of the object (Resource group, resource, task) |
Total | The total assignment for a resource |
Dates | The total assignments for a resource per day and the assignmets for the resource per task. |
Editing data
The task description and progress can be edited using the context menu.
Configuration
Using the context menu, the view can be configured using the configure dialog.
The configure dialog enables you to include or exclude assignments. |