Hvis fordelingen er sat til 'Ingen', så bruges opgavens estimat som det er under skemalægningen. Hvis fordelingen er sat til 'PERT', så beregnes det anvendte estimat (E) ud fra de angivne optimistiske (O), pessimistiske (P) og mest sandsynlige (M) estimat. Den anvendte formel er: