The Project performance view is a project management chart where can be understood the actual situation of the project according the Earned Value Method.
 
===Description===
 
The Project performance view is a project management chart where can be understood the actual situation of the project according to the Earned Value Method.


[[Image:Plan_project_perf_chart.png|300px|thumb]]
[[Image:Plan_project_perf_chart.png|300px|thumb]]
Line 14: Line 17:
*SPI is the Schedule Performance Index.
*SPI is the Schedule Performance Index.


----
{{Plan/Prevnext|prevpage=Schedules Editor|indextext=Contents|nextpage=Task Performance View}}
{|
 
|width="70%"| 
|[[Plan/Manual/Task Performance View|Next]]
|-
|width="70%| 
|Task Performance View
|}
[[Category:Office]]
[[Category:Office]]

Latest revision as of 11:06, 1 November 2019

Project Performance View

Description

The Project performance view is a project management chart where can be understood the actual situation of the project according to the Earned Value Method.

where:

  • BCWS means Budgeted Cost Work Scheduled,
  • BCWP means Budgeted Cost Work Performed,
  • ACWP means Actual Cost Work Performed.

All these are considered as effort in hours and costs.

PI are the Performance Indexes, where:

  • CPI is the Cost Performance Index,
  • SPI is the Schedule Performance Index.