Plan/Engineering To Order project tutorial/executing: Difference between revisions
No edit summary |
No edit summary |
||
Line 1: | Line 1: | ||
<languages /> | |||
<translate> | |||
== Executing and controlling == | == Executing and controlling == | ||
Line 154: | Line 156: | ||
[[Category:Tutorials]] | [[Category:Tutorials]] | ||
[[Category:Office]] | [[Category:Office]] | ||
</translate> |
Revision as of 19:23, 28 December 2010
Executing and controlling
It's time to start our project. After certain time we collect the information needed as completion percentage, worked hours, expenses.
Gantt chart
Now, as we have the baseline, we have prepared all the data needed for the next step which is controlling the working process! Before this, we have to check if everything is right. Looking at the Gantt chart we can see a big picture about our project and therefore be able to visually view if there are some errors.
So, have a look at the Gantt in
, which should be like this
You can also configure the Gantt view to show scheduling errors!
If everything looks right, we can proceed forward.
Project performance chart
At this point the Project Performance Chart shows the baseline and the state before start. It should be like this:
Where BCWS means Budgeted Cost Work Scheduled, BCWP means Budgeted Cost Work Performed, ACWP means Actual Cost Work Performed. All these are considered as effort and costs. PI are the Performance Indexes, where CPI is the Cost Performance Index and SPI is the Schedule Performance Index.
Task performance chart
On the
we can analyse deeply each task or group of tasks with the same index as before.This is really useful in long and complicated project.
Task status
In the
, you can check the actual situation of the project. Can be used as a daily check!
>
Is it time to simulate some work now!
So, let's start to enter some value, right clicking on the activity in the
mec design and choose from the menu that appears. This will appear!
In this task progress window, we can choose to define the starting date of the task. Click on the
button on the upper right corner of the window and choose the date.Than we choose to add a completion percentage for the task, clicking on the add entry in the tab completion. Then click on the
field and move the cursor that appears up to 20%. On the field at the right you can insert the effort used, in this case we will insert 32.The final window will be like this one:
Now we do the same for the second task that can be started, the "ele design". But for this task we choose the edit mode as and compile the relative tab with 5 hours per day on Tue, Wed and Thu. The result will be like below:
Then we move briefly to the and choose the task and insert the progression using the edit mode. Choosing the date we started and the % complete to 10%, the effort will be calculated automatically and the result should be like below:
then moving to the
menu we'll find the following:
Task execution
In the task execution we can have a general view of the things going on.
This is a reasonable view to have a general check!
Gantt
The Gantt menu is a typical Gantt diagram where you can have a clear picture about the sequence and the duration of the project. With our example, it will be like this.
To have a better view of the Gantt diagram, it's possible to work on the zoom. This can be done by right-clicking on the upper part of the diagram where there are the months and days. This menù will appear:
[Image:kplato_gantt3.png|center|500px]]
With this menu it's possible to change the scale or the zoom in/out. Most useful could be the "zoom..." selection that can zoom in or out by a small menu. Try it!!
Milestone Gantt
Milestone Gantt is a part of the Gantt diagram with a filter only to the milestones. In this project we do not have any, so the window will be blank!
Resource assignment
The Resource Assignment view let's you check which resource is used in which day, how many hours and for what.
On the right window, between brackets are the hours of availability while just before the brackets the hours used for that resource.
Resource assignment gantt
The Resource Assignment Gantt is a Gantt diagram with the resource data. Can be useful to visualise the working period of the resources as well as quickly check about some availability to anticipate some tasks!
In this view we can see that the first resource is fully used for the first 3 days as in the main row related to the resource is written 1.0, this means 100%. then on the sub rows of the resource we can see the tasks and the time spent for each task.
Cost breakdown
The Cost Breakdown view represents the result of the accounting of the various tasks cost, generated according the cost assignment in the task and the cost breakdown structure that we decided at the beginning of the job.
On the left windows, in the total column, between brackets there's the total sum for the project according the task, while just before the brackets is the actual total expenses.
Reports
Reports are still in a early stage but you can choose to export as pdf some views, which can be good as the report!