Task Execution View
Description
The Task Execution View is used to inspect task performance information. |
Data
Progress information can be edited in-line as described here or by using the task progress dialog. |
The following columns are displayed as default:
Column | Description |
Name | The name of the task. |
Status | Task status |
% Completed | Task completion |
Responsible | The person responsible for this task. |
Assignment | The resources assigned to this task. |
SPI | Schedule Performance Index. (BCWP / BCWS) |
BCWS | Budgeted Cost of Work Scheduled. |
BCWP | Budgeted Cost of Work Performed. |
ACWP | Actual Cost of Work Performed. |
Description | Task description |
Configuration
Using the context menu, the view can be configured to show / hide the Project, split / unsplit the tree view or it can be configured using the configure dialog.
The configure dialog enables you to tailor the amount of information the view displays to fit your needs. |