Plan/Manual/Task Execution View

From KDE Wiki Sandbox
< Plan‎ | Manual
Revision as of 10:33, 1 November 2019 by Yurchor (talk | contribs) (Fix minor typo)

Task Execution View

Description

The Task Execution View is used to inspect task performance information.

Data

Progress information can be edited in-line as described here or by using the task progress dialog.


The following columns are displayed as default:

Column Description
Name The name of the task.
Status Task status
% Completed Task completion
Responsible The person responsible for this task.
Assignment The resources assigned to this task.
SPI Schedule Performance Index. (BCWP / BCWS)
BCWS Budgeted Cost of Work Scheduled.
BCWP Budgeted Cost of Work Performed.
ACWP Actual Cost of Work Performed.
Description Task description

Configuration

Using the context menu, the view can be configured to show / hide the Project, split / unsplit the tree view or it can be configured using the configure dialog.


The configure dialog enables you to tailor the amount of information the view displays to fit your needs.