Plan/Manual/Task Performance View

From KDE Wiki Sandbox
< Plan‎ | Manual
Revision as of 13:30, 29 November 2011 by Dag (talk | contribs)

Task performance chart

On the task performance chart we can analyze deeply each sub task or task with the same indexes as for the project performance view. This is really useful in long and complicated project

On the left window you can choose each single sub task as well as an entire task, than on the right window will appear the corresponding chart.

where:

  • BCWS means Budgeted Cost Work Scheduled,
  • BCWP means Budgeted Cost Work Performed,
  • ACWP means Actual Cost Work Performed.

All these are considered as effort in hours and costs.

PI are the Performance Indexes, where:

  • CPI is the Cost Performance Index,
  • SPI is the Schedule Performance Index.

Next
Task Status View