Translations:Plan/Engineering To Order project tutorial/planning/108/en

From KDE Wiki Sandbox
Revision as of 08:40, 11 April 2019 by FuzzyBot (talk | contribs) (Importing a new version from external source)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

If direction is Forward, the project is scheduled starting at the projects earliest start time specified in the main project dialog. If direction is Backward, the project is scheduled starting at the projects latest finish time specified in the main project dialog.