Translations:Plan/Engineering To Order project tutorial/planning/112/en

From KDE Wiki Sandbox

If distribution is 'None', the tasks estimate is used as is during scheduling. If distribution is 'PERT', the estimate (E) used is calculated based on the entered optimistic- (O), pessimistic-(P) and most likely (M) estimate. The formula used for this is: