Plan/Engineering To Order project tutorial/planning/it: Difference between revisions
(Importing a new version from external source) |
(Updating to match new version of source page) |
||
(41 intermediate revisions by 2 users not shown) | |||
Line 26: | Line 26: | ||
{{Tip | {{Tip|1=Remember to press <keycap>Ctrl + S</keycap> to save the file sometime!! '''Plan''' regularly updates a backup file in case it crashes}} | ||
Line 97: | Line 97: | ||
[[Image:cbs1.png|center|800px]] | [[Image:cbs1.png|center|800px]] | ||
Play with the <menuchoice>Add Account</menuchoice> and <menuchoice>Add Subaccount</menuchoice> icons to reach the full tree! This is a personal approach for a complete ETO project due to my experience. | |||
Per esempio puoi avere un conto "dipendente diretto" per gestire il costo del tuo dipendente o puoi avere idea del costo dei tuoi fornitori non appena inserisci il loro lavoro utilizzando un conto dedicato. | Per esempio puoi avere un conto "dipendente diretto" per gestire il costo del tuo dipendente o puoi avere idea del costo dei tuoi fornitori non appena inserisci il loro lavoro utilizzando un conto dedicato. | ||
Line 107: | Line 107: | ||
Puoi accedere alla finestra delle risorse facendo clic sulla voce <menuchoice>Risorse</menuchoice> nella parte sinistra della finestra, appena sotto all'elemento Struttura funzionale dei costi premuto prima. | Puoi accedere alla finestra delle risorse facendo clic sulla voce <menuchoice>Risorse</menuchoice> nella parte sinistra della finestra, appena sotto all'elemento Struttura funzionale dei costi premuto prima. | ||
The resources are organized as ''resource groups'' and ''resources''. So, first we insert the team group as resource group clicking on the <menuchoice>Add Resource Group</menuchoice> icon for each item as below. | |||
[[Image:res6.png|center|400px]] | [[Image:res6.png|center|400px]] | ||
Line 130: | Line 130: | ||
{{Tip | {{Tip|1=As entering resource characteristics is a long work that probably is needed for other project, it might be better to maintain you resources in a separate file and insert them when you start a new project using <menuchoice>Tools -> Insert Project File</menuchoice>. This will preserve the (internal) identity of the resources which may come in handy if you want to coordinate multiple projects later. See [[Special:myLanguage/Plan/Manual/Managing_Resources|Managing Resources]]}} | ||
==== Risorse del materiale ==== | ==== Risorse del materiale ==== | ||
Line 156: | Line 156: | ||
Il costo dello straordinario non è ancora implementato.<!--? ...si spera--> | Il costo dello straordinario non è ancora implementato.<!--? ...si spera--> | ||
=== | === Attività === | ||
Ora è tempo delle attività! | |||
Puoi accedere alla finestra delle attività facendo clic sulla voce "Attività" sul lato sinistro della finestra, appena sotto alla voce Risorse premuta prima. | |||
Dobbiamo inserire le seguenti voci: | |||
[[Image:task1.png|center|800px]] | [[Image:task1.png|center|800px]] | ||
Man mano che inseriamo ogni nome, possiamo modificare ciascuna voce facendo clic destro sul nome. Apparirà la seguente sulla prima attività: | |||
[[Image:task2.png|center|400px]] | [[Image:task2.png|center|400px]] | ||
Ci sono cinque schede: Generale, Risorse, Documenti, Costo e Descrizione. | |||
Nella scheda Generale inseriamo il nome dell'attività, puoi scegliere una persona responsabile se necessario, poi definiamo i tempi e il rischio associato all'attività. La modalità di gestione del tempo è tipica della pianificazione, la più usata è "appena possibile". Altri tipi di modalità comportano la necessità di compilare la data e l'ora a destra del menu a comparsa. | |||
La stima è il tempo necessario per completare l'attività, può essere in differenti unità: o (ore), g (giorni), s (settimane) e M (mesi). | |||
{{Note|1= | {{Note/it|1=La stima può essere in lavoro o durata. Il lavoro è la necessità di tempo lavorativo per un'attività, la durata è la durata del lavoro per un'attività. La principale differenza è che se per un lavoro utilizzi due lavoratori, il tempo totale viene dimezzato! Se hai impostato per durata, il tempo totale sarà lo stesso anche se utilizzi più lavoratori. Questo implicitamente influisce sul costo dell'attività.}} | ||
Il livello di rischio così come i tempi ottimistici e pessimistici modificheranno il calcolo del progetto totale considerando la tecnica PERT. In questo caso -5% e 20% sono i valori e il rischio è considerato "Alto". | |||
Line 186: | Line 186: | ||
Nella scheda Risorse scegliamo la risorsa che desideriamo utilizzare oltre alla sua disponibilità in % e le eventuali risorse associate. | |||
Line 192: | Line 192: | ||
Nella scheda Documenti possiamo aggiungere collegamenti a documenti pertinenti all'attività. Non è utilizzata nella nostra guida. | |||
Line 198: | Line 198: | ||
La quarta scheda è quella relativa al Costo. Qui possiamo associare il costo in esecuzione dell'attività ad un conto precedentemente definito nella "Struttura funzionale dei costi". | |||
Possiamo anche scegliere di aggiungere un costo all'avvio e alla chiusura dell'attività che può essere associato a un diverso conto. | |||
{{Note|1= | {{Note/it|1=I costi all'avvio e alla chiusura sono integrati nel BCWS}} | ||
Line 209: | Line 209: | ||
L'ultima scheda è la Descrizione in cui possiamo inserire i nostri commenti, principalmente l'elenco delle consegne correlate all'attività. | |||
=== | === Dipendenze === | ||
Ora è tempo di suddividere per priorità le attività! Facciamo clic sulla voce <menuchoice>Dipendenze (grafico)</menuchoice> a sinistra nella finestra principale. | |||
Dunque questo è quello che dovrebbe apparire appena apri la finestra a destra. | |||
[[Image:kplato_dep1.png|center|800px]] | [[Image:kplato_dep1.png|center|800px]] | ||
Iniziamo a dare priorità alle attività in modo da avere un elenco completo delle dipendenze. Puoi far ciò graficamente con il mouse, facendo clic sulla parte destra o sinistra dell'attività e poi trascinando la relativa freccia nella posizione desiderata dell'altra attività. Dovrebbe essere meglio connettere solo le attività e non il sommario. Il risultato dovrebbe essere come qui sotto. | |||
[[Image:kplato_dep3.png|center|800px]] | [[Image:kplato_dep3.png|center|800px]] | ||
=== | === Pianificazione === | ||
Wow | Wow! Ora è il momento di pianificare e preparare il rilascio<!--secondo la gui--> del progetto! | ||
Facendo clic a sinistra su <menuchoice>Pianificazioni</menuchoice> passerai alla pianificazione delle attività. | |||
Ora creiamo una nuova pianificazione facendo clic sul pulsante <menuchoice>Aggiungi pianificazione</menuchoice> nella parte alta della finestra, poi scegliamo un'analisi <menuchoice>PERT</menuchoice> per il tipo di distribuzione e quindi facciamo clic sul pulsante <menuchoice>Calcola</menuchoice>. Appena finito il calcolo premi il pulsante <menuchoice>Rilascio</menuchoice> in alto nella finestra. Il risultato sarà come questo: | |||
[[Image:kplato_sched1.png|center|800px]] | [[Image:kplato_sched1.png|center|800px]] | ||
{{Tip|1= | {{Tip/it|1=Controlla sempre il registro della pianificazione per cercare qualche messaggio di errore nella colonna "Severità", potrebbe essere utile.}} | ||
Here, for reference, is a copy from the | Here, for reference, is a copy from the [[Special:myLanguage/Plan/Manual/Schedules Editor|Plan manual]] of the field's definitions in the schedule | ||
{| style="border-spacing:0;" | {| style="border-spacing:0;" | ||
| style="background-color:#efefef;border-top:0.035cm solid #808080;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| ''' | | style="background-color:#efefef;border-top:0.035cm solid #808080;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| '''Colonna''' | ||
| style="background-color:#efefef;border:0.035cm solid #808080;padding:0.132cm;"| ''' | | style="background-color:#efefef;border:0.035cm solid #808080;padding:0.132cm;"| '''Descrizione'''<!--}--> | ||
|- | |- | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| Nome | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| Nome della pianificazione | ||
|- | |- | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| Stato | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| Stato della pianificazione. Mostra una barra di avanzamento durante la pianificazione. | ||
|- | |- | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| Direzione | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| Direzione della pianificazione | ||
Se la direzione è Avanti, il progetto è pianificato a partire dai progetti specificati per primi temporalmente nella finestra di dialogo del progetto principale. Se la direzione è Indietro, il progetto è pianificato a partire dai progetti specificati per ultimi nella finestra del progetto principale. | |||
|- | |- | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| Sovraprenotazione | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| Controlla le risorse sovraprenotate durante la pianificazione | ||
Se la sovraprenotazione è permessa, una risorsa potrebbe essere prenotata (in giorni lavorativi) per lavorare più di quanto possibile. Può succedere se la risorsa è assegnata a più attività o prenotata in altri progetti. Se la sovraprenotazione è da evitare, le risorse non verranno prenotate più di quanto possibile. In un conflitto di risorse le attività verranno rimandate fino a quando la risorsa tornerà disponibile. | |||
|- | |- | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| Distribuzione | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| La distribuzione da utilizzare durante la pianificazione | ||
Se la distribuzione è 'Nessuna', la stima delle attività viene utilizzata così com'è durante la pianificazione. Se la distribuzione è 'PERT', la stima (E) utilizzata viene calcolata basandosi sulle stime inserite ottimistica- (O), pessimistica-(P) e principale (M). La formula utilizzata è: | |||
E = (O + 4 * M + P) / 6. | E = (O + 4 * M + P) / 6. | ||
|- | |- | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| Inizio previsto | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| Il tempo di inizio pianificato | ||
|- | |- | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| Fine prevista | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| La fine pianificata | ||
|- | |- | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:none;padding:0.132cm;"| Pianificatore | ||
| style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| | | style="background-color:transparent;border-top:none;border-bottom:0.035cm solid #808080;border-left:0.035cm solid #808080;border-right:0.035cm solid #808080;padding:0.132cm;"| Il pianificatore utilizzato per calcolare la pianificazione del progetto | ||
Il pianificatore predefinito incluso è il Network Scheduler. Un altro pianificatore attualmente disponibile è RCPS se libRCPS è installata nel sistema. RCPS è un pianificatore di progetto per gestire risorse<!--basato sulla generica-->. | |||
<!--{-->|} | <!--{-->|} | ||
Dunque ora abbiamo finito la nostra pianificazione delle attività per il progetto! | |||
[[Category:Guide/it]] | [[Category:Guide/it]] | ||
[[Category:Ufficio/it]] | [[Category:Ufficio/it]] |
Latest revision as of 09:30, 11 April 2019
La fase di pianificazione
Inizio
Quando apri il programma per la prima volta, comparirà la finestra sottostante.
Scegliamo il modello
per iniziare.Impostazione del progetto principale
Diamo quindi un nome e un responsabile al progetto e impostiamo alcune altre informazioni generali. Per far questo hai bisogno di fare clic sull'icona
in alto a sinistra nella schermata. Comparirà quindi la seguente finestra:
In questa finestra possiamo scrivere il nome del progetto, scegliere un responsabile da un elenco già presente nel sistema (se hai KDE e Kontact) o scrivere un nuovo nome secondo quello che ti è più comodo.
Gli obiettivi temporali Avvio iniziale e Fine al più tardi sono utilizzati per pianificare il progetto. Vogliamo pianificare in avanti, dunque imposteremo avvio iniziale a quando vogliamo che il progetto abbia inizio e termine ultimo a quando il progetto dovrebbe finire. Se il progetto non può essere pianificato per essere terminato prima di questa data, verrà proposto un messaggio di avvertimento.
Nella parte inferiore della finestra può essere inserito un commento sul progetto. Questi dati verranno utilizzati per i resoconti o per altri scopi generali durante il periodo di lavoro.
Impostazione della valuta
Possiamo scegliere di lavorare con differenti valute. Come inglese è impostata su $, noi abbiamo bisogno di passare a €. Per far questo dobbiamo selezionare il menu
e apparirà la finestra sottostante.
Modifica quindi il simbolo della valuta da $ a € e fai clic su dato che le altre impostazioni vanno bene.
Calendario di lavoro
Dai un'occhiata al calendario di lavoro e vacanze in
nella parte superiore sinistra della finestra sotto il gruppo . Comparirà la seguente vista:
Al centro possiamo aggiungere diversi calendari per differenti fusi orari e settimane di lavoro. A destra è disponibile un calendario mensile, sulla parte in alto c'è la configurazione per le ore di lavoro settimanale, tipicamente 8 ore da lunedì a venerdì e giorni non lavorativi per sabato e domenica.
Aggiungiamo un nuovo calendario per i nostri scopi futuri facendo clic sull'icona
, scriviamo poi come nomeInstallazione
e come fuso orario scegliamo
dal menu di selezione.
Ora abbiamo bisogno di selezionare il calendario installazione e di definire la relativa settimana lavorativa.
Nell'angolo a destra in alto del calendario ci sono alcuni spazi indicanti una tipica settimana di lavoro.
Fai clic destro su quello vuoto sotto l'indicazione Lunedì e comparirà un menu con la possibilità di scegliere tra , e .
Fai clic su
e apparirà la seguente finestra
Aggiungiamo le tipiche ore lavorative per un lavoro di installazione. 10 ore al giorno da lunedì a sabato e 4 ore di domenica. In caso di necessità possiamo anche scegliere di inserire l'orario di pausa.
Dunque a partire dalle 7 per 10 ore e poi facciamo clic su
e quindi .Ripetiamo lo stesso per gli altri giorni fino al sabato, mentre per la domenica inseriamo 4 ore dalle 8 di mattina.
Puoi anche selezionare più giorni o giorni feriali utilizzando Shift + pulsante sinistro del mouse o Ctrl + pulsante sinistro del mouse.
Possiamo anche fare clic destro su una data nel calendario e fare le stesse considerazioni relative ai giorni o all'orario di lavoro e non. Questo è particolarmente necessario quando hai bisogno di lavorare con vacanze differenti dalle tue!
In ogni caso il risultato finale dovrebbe essere simile all'immagine sottostante:
Struttura funzionale dei costi
Qui definiamo quali saranno i centri di costo che desideriamo utilizzare nel progetto. Possiamo avere diversi gruppi e sottogruppi.
Fai clic sull'elemento
nel lato sinistro della finestra, proprio sotto all'elemento Lavoro e vacanze che hai premuto prima.Secondo le necessità di gestione dei costi, dividiamo le strutture dei costi nel modo seguente
Play with the
and icons to reach the full tree! This is a personal approach for a complete ETO project due to my experience.Per esempio puoi avere un conto "dipendente diretto" per gestire il costo del tuo dipendente o puoi avere idea del costo dei tuoi fornitori non appena inserisci il loro lavoro utilizzando un conto dedicato.
Risorse
Dunque ora è tempo di definire il nostro gruppo di lavoro e il materiale!
Puoi accedere alla finestra delle risorse facendo clic sulla voce
nella parte sinistra della finestra, appena sotto all'elemento Struttura funzionale dei costi premuto prima.The resources are organized as resource groups and resources. So, first we insert the team group as resource group clicking on the
icon for each item as below.Appena completi il gruppo è tempo di inserire le persone e il materiale!
Risorse di lavoro
Ora è il momento di modificare ogni singola risorsa con lo scopo di definirla. Fai clic destro sul nome della risorsa per aprire la finestra Impostazioni della risorsa.
Quindi aggiungiamo le iniziali e l'indirizzo di posta elettronica, passiamo a
, inseriamo il costo secondo necessità. Il conto è impostato su dato che in questo caso non addebitiamo il costo ad uno specifico conto dei costi.
Ricorda che le risorse dell'installazione ci sarà un calendario differente, "installazione", che abbiamo inserito prima!
Risorse del materiale
Abbiamo deciso di aggiungere i macchinari di laboratorio per considerare alcuni costi oltre al loro utilizzo.
A questo scopo tra le risorse aggiungiamo il laboratorio come materiale e un macchinario CNC oltre a un pacchetto di strumenti di montaggio.
Preferenze per il calendario
Un'altra cosa interessante da notare è che utilizziamo diversi calendari per differenti risorse.
Il calendario dell'attività ha la precedenza su quello della risorsa. La data di disponibilità di una risorsa dipende in gran parte dalla possibilità che questa risorsa sia disponibile solo per un periodo di tempo. In questo caso abbiamo bisogno di essere sicuri che tutte le risorse siano disponibili dall'inizio alla fine del lavoro.
Il costo dello straordinario non è ancora implementato.
Attività
Ora è tempo delle attività!
Puoi accedere alla finestra delle attività facendo clic sulla voce "Attività" sul lato sinistro della finestra, appena sotto alla voce Risorse premuta prima.
Dobbiamo inserire le seguenti voci:
Man mano che inseriamo ogni nome, possiamo modificare ciascuna voce facendo clic destro sul nome. Apparirà la seguente sulla prima attività:
Ci sono cinque schede: Generale, Risorse, Documenti, Costo e Descrizione.
Nella scheda Generale inseriamo il nome dell'attività, puoi scegliere una persona responsabile se necessario, poi definiamo i tempi e il rischio associato all'attività. La modalità di gestione del tempo è tipica della pianificazione, la più usata è "appena possibile". Altri tipi di modalità comportano la necessità di compilare la data e l'ora a destra del menu a comparsa.
La stima è il tempo necessario per completare l'attività, può essere in differenti unità: o (ore), g (giorni), s (settimane) e M (mesi).
Il livello di rischio così come i tempi ottimistici e pessimistici modificheranno il calcolo del progetto totale considerando la tecnica PERT. In questo caso -5% e 20% sono i valori e il rischio è considerato "Alto".
Nella scheda Risorse scegliamo la risorsa che desideriamo utilizzare oltre alla sua disponibilità in % e le eventuali risorse associate.
Nella scheda Documenti possiamo aggiungere collegamenti a documenti pertinenti all'attività. Non è utilizzata nella nostra guida.
La quarta scheda è quella relativa al Costo. Qui possiamo associare il costo in esecuzione dell'attività ad un conto precedentemente definito nella "Struttura funzionale dei costi".
Possiamo anche scegliere di aggiungere un costo all'avvio e alla chiusura dell'attività che può essere associato a un diverso conto.
L'ultima scheda è la Descrizione in cui possiamo inserire i nostri commenti, principalmente l'elenco delle consegne correlate all'attività.
Dipendenze
Ora è tempo di suddividere per priorità le attività! Facciamo clic sulla voce
a sinistra nella finestra principale.Dunque questo è quello che dovrebbe apparire appena apri la finestra a destra.
Iniziamo a dare priorità alle attività in modo da avere un elenco completo delle dipendenze. Puoi far ciò graficamente con il mouse, facendo clic sulla parte destra o sinistra dell'attività e poi trascinando la relativa freccia nella posizione desiderata dell'altra attività. Dovrebbe essere meglio connettere solo le attività e non il sommario. Il risultato dovrebbe essere come qui sotto.
Pianificazione
Wow! Ora è il momento di pianificare e preparare il rilascio del progetto!
Facendo clic a sinistra su
passerai alla pianificazione delle attività.Ora creiamo una nuova pianificazione facendo clic sul pulsante
nella parte alta della finestra, poi scegliamo un'analisi per il tipo di distribuzione e quindi facciamo clic sul pulsante . Appena finito il calcolo premi il pulsante in alto nella finestra. Il risultato sarà come questo:
Here, for reference, is a copy from the Plan manual of the field's definitions in the schedule
Colonna | Descrizione |
Nome | Nome della pianificazione |
Stato | Stato della pianificazione. Mostra una barra di avanzamento durante la pianificazione. |
Direzione | Direzione della pianificazione
Se la direzione è Avanti, il progetto è pianificato a partire dai progetti specificati per primi temporalmente nella finestra di dialogo del progetto principale. Se la direzione è Indietro, il progetto è pianificato a partire dai progetti specificati per ultimi nella finestra del progetto principale. |
Sovraprenotazione | Controlla le risorse sovraprenotate durante la pianificazione
Se la sovraprenotazione è permessa, una risorsa potrebbe essere prenotata (in giorni lavorativi) per lavorare più di quanto possibile. Può succedere se la risorsa è assegnata a più attività o prenotata in altri progetti. Se la sovraprenotazione è da evitare, le risorse non verranno prenotate più di quanto possibile. In un conflitto di risorse le attività verranno rimandate fino a quando la risorsa tornerà disponibile. |
Distribuzione | La distribuzione da utilizzare durante la pianificazione
Se la distribuzione è 'Nessuna', la stima delle attività viene utilizzata così com'è durante la pianificazione. Se la distribuzione è 'PERT', la stima (E) utilizzata viene calcolata basandosi sulle stime inserite ottimistica- (O), pessimistica-(P) e principale (M). La formula utilizzata è: E = (O + 4 * M + P) / 6. |
Inizio previsto | Il tempo di inizio pianificato |
Fine prevista | La fine pianificata |
Pianificatore | Il pianificatore utilizzato per calcolare la pianificazione del progetto
Il pianificatore predefinito incluso è il Network Scheduler. Un altro pianificatore attualmente disponibile è RCPS se libRCPS è installata nel sistema. RCPS è un pianificatore di progetto per gestire risorse. |
Dunque ora abbiamo finito la nostra pianificazione delle attività per il progetto!